Summary: Fundamental data of scaffolding system and Structural Requirements of Scaffolding ,
The scaffolding use 48*3 steel tubes and couplers to build the double line scaffolding frame and the downside will be supported by horizontal cantilevered beams made of 16 I shape steel whose end will be welded with two short reinforced steel bar and the space will  be equal to the transverse space so the steel tube can be coated in.

Fundamental data of scaffold system:
For scaffolding with single tube of standing tubes or tubular scaffolding with couplers, the width of frame shall be 1050mm, lift of 1800 and maximum longitudinal space of 1800mm. Inside standing tubes shall be 350mm away to the wall. From the ground floor to the third floor shall use temporary floor type scaffolding and above the third floor shall use 16 I shape cantilevered scaffolding.

Structural requirement:
The first part is the cantilevered I shape cantilevered scaffolding which bears the major working load and the other is working platform supported by I shape steel frame. They can bear all the working load including the wind load.  are the two scaffolding kinds which are widely used in the construction projects. And the staircase scaffolding is the fast building product which can help to accelerate the building speed of the whole project. And for some other projects which do not emphasize on the process efficiency, they will adopt the frame scaffolding. The two kinds differ greatly in the investment, time, working force and energy. The staircase scaffolding is the new kind devised to solve above mentioned problems to avoid unnecessary connection effort between auxiliary elements so the whole connection will be much easier and simpler, saving both time and energy.

Previous:The scaffolding advantages and features

Next:What shortcomings does the frame scaffolding have when compared with staircase scaffolding